Port Solent Marina Dredging Plans

Date:

Port Solent is set to undertake its annual dredging programme to ensure that most boats will be able to use the lock 24/7 during most states of the tide. The dredging is booked provisionally for the week commencing Monday 24th February and will be undertaken by ML Dredging following the results of a survey which will be conducted by Shoreline Surveys on the week commencing 13th January. These dates are subject to change.

The plan for the dredging is to remove approximately 7,450mof silt from the entrance channel to the marina.