We are delighted to confirm one of the first major milestones in the development of Noss on Dart Marina is now complete. At the end of March, the last of the new piles required to complete the new floating marina were driven into the river bed, now in place ready for the onsite contractors Walcon Marine to complete work on the final pontoons. 

Noss Pontoons 21.03.21 NW Mixed Content Block 952X664

General Manager, Andy Osman CMM comments: “Having the final piles now driven is a significant milestone for us to have achieved particularly over the winter period and within the parameters of our MMO licence. It is really exciting to see Premier’s vision for Noss on Dart coming to life.

“With over 100 piles driven in total, work is now progressing to install the last remaining pontoons and accompanying services, with the hope that the new marina will be fully open for business later this summer."