Pontoon Re-decking Completed

Date:

Phase 4 of the pontoon re-decking is now complete. Taking place over 7 weeks the project saw 3000 new timber boards installed on the main walkways, hammerheads and ramps of X, Y and Z pontoons and the outer waiting pontoon.

Premier invested £50,000 in phase 4 of the 5 phase programme both to bring the pontoons up to Premier standard and to provide a more stable platform on which to manoeuvre trolleys.

The fifth and final phase of the pontoon re-decking will start in Winter 2019/20 and will see pontoons AA, A, B, C and D re-decked as well as the inner waiting pontoon. This work is important to Premier and we believe it will lead to a more pleasant experience for both berth holders and guests of the marina.