The regeneration of Noss on Dart is now in full flow. Following completion of the railway bridge, the team is focused on constructing both the new access road (from the entrance of the site to the railway bridge) and the woodland car parking.

Demolition is also well underway with the Green Shed, Noss House, the Philips Building, and the former Platers’ and Welders’ Shops scheduled for the first phase of demolition. All of these important enabling works are expected to be completed by the end of April 2019 and will facilitate the development of the new boatyard, decked car park and commercial buildings which will follow.